Featured image for Supreme Court Judgment dated 29-03-2019 in case of petitioner name Union of India vs Parmar Construction Company
| |

Supreme Court Upholds Arbitration Clauses in Government Contracts: Impact on Construction Disputes

The Supreme Court of India, in a landmark ruling in Union of India vs. Parmar Construction Company, addressed crucial issues regarding arbitration agreements in government contracts. This case involved disputes concerning construction projects undertaken by contractors for the Indian Railways and the application of the Arbitration and Conciliation Act, 1996. The ruling provides clarity on how arbitration clauses must be adhered to in public contracts and the limited scope of judicial intervention.

The Court examined whether the High Court was justified in appointing an independent arbitrator under Section 11(6) of the Arbitration and Conciliation Act, despite an existing arbitration agreement specifying the appointment procedure. Additionally, the ruling explored the enforceability of ‘No Claim Certificates’ signed by contractors under alleged financial duress.

Background of the Case

The case arose from multiple disputes between contractors and the Indian Railways, wherein contractors alleged non-payment of dues, arbitrary deductions, and unfair contract terms. The primary issues in the case were:

  • Non-payment of final bills and security deposits.
  • Unilateral deductions by the Indian Railways.
  • Alleged coercion in obtaining ‘No Claim Certificates’ from contractors.
  • Appointment of arbitrators from within the government entity, raising concerns of bias.

The contractors, invoking the arbitration clause in their contracts, sought dispute resolution. However, the Indian Railways refused to appoint arbitrators, arguing that the disputes had been settled through the execution of No Claim Certificates. As a result, the contractors moved the High Court under Section 11(6) of the Arbitration Act, leading to the appointment of independent arbitrators.

Petitioner’s Arguments (Union of India)

The Union of India, representing the Indian Railways, presented the following arguments:

  • Arbitration Agreement Supremacy: The arbitration clauses in the contracts explicitly prescribed the procedure for appointing arbitrators. The High Court should not have intervened by appointing independent arbitrators.
  • No Claim Certificates: The contractors had voluntarily signed No Claim Certificates, confirming that they had no pending claims.
  • Judicial Overreach: The High Court overstepped its jurisdiction by overriding an agreed contractual procedure.
  • 2015 Arbitration Act Amendments: The amendments requiring neutrality in arbitrator appointments did not apply retrospectively to contracts executed before October 23, 2015.

Respondent’s Arguments (Contractors)

The contractors countered the Railways’ claims with the following arguments:

  • Coercion in No Claim Certificates: The certificates were signed under financial duress as a condition for receiving payments.
  • Biased Arbitrator Appointments: The arbitration clauses mandated the appointment of railway officials as arbitrators, violating principles of fairness and neutrality.
  • Right to Fair Arbitration: The High Court correctly appointed independent arbitrators to ensure an impartial dispute resolution process.
  • Delays in Dispute Resolution: The Railways’ refusal to appoint arbitrators justified judicial intervention.

Supreme Court’s Observations

The Supreme Court examined the arbitration agreement and upheld its binding nature. It ruled:

“The arbitration agreement must be honored unless there are exceptional circumstances that justify judicial intervention. The appointment procedure prescribed in the contract cannot be bypassed merely because one party finds it unfavorable.”

On the validity of No Claim Certificates, the Court stated:

“No Claim Certificates do not automatically preclude arbitration, especially if evidence suggests they were signed under duress. However, contractors must provide concrete proof of coercion.”

Regarding the High Court’s intervention, the Court observed:

“The High Court was not justified in directly appointing an independent arbitrator without first ensuring that the procedure in the arbitration clause was exhausted.”

Final Judgment

The Supreme Court ruled in favor of the Union of India and issued the following orders:

  • The High Court’s orders appointing independent arbitrators were quashed.
  • The Railways was directed to appoint arbitrators as per the arbitration clause within one month.
  • Contractors were allowed to submit claims before the appointed arbitrators.
  • The arbitration proceedings must be completed within six months to ensure timely resolution.

The Court concluded:

“Arbitration should proceed as per the contractual agreement, and courts should intervene only when procedural fairness is compromised.”

Implications of the Verdict

This ruling has several significant implications:

  • Enforcement of Contractual Arbitration: The decision reinforces that courts should not override arbitration clauses unless there are strong grounds for doing so.
  • Protection for Contractors: The Court acknowledged that No Claim Certificates may be challenged if coercion is proven.
  • Judicial Restraint in Arbitration: The ruling limits the power of High Courts to interfere in arbitration proceedings.
  • Timely Dispute Resolution: The Court directed that arbitration must be concluded within six months, ensuring efficiency in dispute resolution.

By upholding arbitration agreements while ensuring fairness, this ruling provides critical guidance for government contracts and construction disputes in India.


Petitioner Name: Union of India.
Respondent Name: Parmar Construction Company.
Judgment By: Justice A.M. Khanwilkar, Justice Ajay Rastogi.
Place Of Incident: Rajasthan.
Judgment Date: 29-03-2019.

Don’t miss out on the full details! Download the complete judgment in PDF format below and gain valuable insights instantly!

Download Judgment: Union of India vs Parmar Construction Supreme Court of India Judgment Dated 29-03-2019.pdf

Direct Downlaod Judgment: Direct downlaod this Judgment

See all petitions in Arbitration Awards
See all petitions in Dispute Resolution Mechanisms
See all petitions in Arbitration Act
See all petitions in Institutional Arbitration
See all petitions in Enforcement of Awards
See all petitions in Judgment by A M Khanwilkar
See all petitions in Judgment by Ajay Rastogi
See all petitions in allowed
See all petitions in Quashed
See all petitions in supreme court of India judgments March 2019
See all petitions in 2019 judgments

See all posts in Arbitration and Alternate Dispute Resolution Category
See all allowed petitions in Arbitration and Alternate Dispute Resolution Category
See all Dismissed petitions in Arbitration and Alternate Dispute Resolution Category
See all partially allowed petitions in Arbitration and Alternate Dispute Resolution Category

Similar Posts