Supreme Court Upholds Arbitration Award in Hindustan Construction vs. NHAI Dispute image for SC Judgment dated 24-08-2023 in the case of Hindustan Construction Company vs National Highways Authority of
| |

Supreme Court Upholds Arbitration Award in Hindustan Construction vs. NHAI Dispute

The Supreme Court of India recently delivered a significant judgment in Hindustan Construction Company Ltd. vs. National Highways Authority of India, ruling in favor of the construction firm in a dispute concerning contract interpretation and arbitration awards. The judgment, delivered by S. Ravindra Bhat and Aravind Kumar, emphasized the importance of minimal judicial interference in arbitration proceedings and upheld the validity of technical expert decisions.

The ruling reaffirms the principle that courts should not substitute their views for those of expert arbitration tribunals unless there is clear evidence of patent illegality or a violation of fundamental legal principles.

Background of the Case

The case arose from a contractual dispute between Hindustan Construction Company Ltd. (HCC) and the National Highways Authority of India (NHAI) concerning the construction of the Allahabad Bypass Project in Uttar Pradesh. The dispute primarily revolved around how measurements should be taken for embankment construction involving soil and pond ash.

Read also: https://judgmentlibrary.com/supreme-court-upholds-arbitration-award-in-maharashtra-road-construction-dispute/

Chronology of Events

  • June 2, 2004: NHAI awarded the construction of the Allahabad Bypass Project to HCC.
  • 2010: Arbitration proceedings began over disputes related to contract interpretation.
  • March 30, 2010: The arbitration tribunal ruled in favor of HCC, awarding compensation for work completed.
  • November 30, 2011: A single judge of the Delhi High Court upheld the arbitration award.
  • November 8, 2012: A Division Bench of the Delhi High Court overturned the single judge’s ruling and set aside the arbitration award.
  • August 24, 2023: The Supreme Court reinstated the arbitration award, ruling in favor of HCC.

Petitioner’s Arguments

The appellant, HCC, represented by Senior Counsels Dr. Abhishek Manu Singhvi, V. Giri, and Anil Airi, contended:

  • The Division Bench of the High Court overstepped its jurisdiction by interfering with the arbitration award.
  • The arbitration tribunal, comprising technical experts, had correctly interpreted the contract terms.
  • The High Court should not have substituted its own interpretation of the contract for that of the tribunal.
  • The contract explicitly provided for composite measurement of embankment cross-sections, as determined by the arbitrators.
  • The High Court’s ruling disregarded the established principle that courts should not interfere with arbitration awards unless there is clear evidence of illegality.

Respondent’s Arguments

The National Highways Authority of India (NHAI), represented by Additional Solicitor General Aishwarya Bhati, countered:

  • The arbitration tribunal’s interpretation of contract clauses was incorrect and led to an unjustified financial burden on NHAI.
  • The High Court’s ruling was correct in holding that embankment materials (soil and pond ash) should be measured separately.
  • Measurement discrepancies were critical, as different embankment materials had different compaction and usage ratios.
  • The tribunal’s decision effectively rewrote contract terms rather than interpreting them.

Supreme Court’s Analysis

The Supreme Court scrutinized whether the High Court was justified in interfering with the arbitration tribunal’s award.

1. Minimal Judicial Interference in Arbitration

The Court emphasized that arbitration awards should not be disturbed unless there is clear evidence of illegality:

“It is well established that courts should not act as appellate forums for arbitration awards unless the award is perverse or patently illegal.”

2. Deference to Technical Expertise

The Court ruled that contract interpretation in technical matters should be left to expert arbitrators:

“Technical aspects of contract execution are best understood by experts in the field. The tribunal’s findings, endorsed by the DRB and technical panels, should be given due weight.”

3. Consistency in Measurement Methodology

The Court held that the contract contemplated a composite approach to embankment measurement:

“The contract specified that embankment measurements must be taken as a whole, rather than separating materials. The tribunal’s findings align with contractual terms.”

4. Limits of High Court’s Review

The Supreme Court ruled that the Division Bench had exceeded its authority:

“The High Court’s role was not to substitute its own view but to determine if the award was perverse. No such perversity exists in this case.”

Final Verdict

The Supreme Court ruled:

  • The arbitration award in favor of HCC was reinstated.
  • The High Court’s decision to set aside the award was quashed.
  • NHAI was directed to pay HCC with 12% interest from the date of the award.
  • The ruling reaffirmed the importance of honoring arbitration awards unless clear illegality is proven.

This judgment sets a precedent for ensuring minimal judicial interference in arbitration and upholding the role of technical experts in contract interpretation.


Petitioner Name: Hindustan Construction Company Ltd..
Respondent Name: National Highways Authority of India.
Judgment By: Justice S. Ravindra Bhat, Justice Aravind Kumar.
Place Of Incident: Allahabad Bypass Project, Uttar Pradesh.
Judgment Date: 24-08-2023.

Don’t miss out on the full details! Download the complete judgment in PDF format below and gain valuable insights instantly!

Download Judgment: hindustan-constructi-vs-national-highways-au-supreme-court-of-india-judgment-dated-24-08-2023.pdf

Directly Download Judgment: Directly download this Judgment

See all petitions in Arbitration Awards
See all petitions in Dispute Resolution Mechanisms
See all petitions in Judgment by S Ravindra Bhat
See all petitions in Judgment by Aravind Kumar
See all petitions in allowed
See all petitions in Quashed
See all petitions in supreme court of India judgments August 2023
See all petitions in 2023 judgments

See all posts in Arbitration and Alternate Dispute Resolution Category
See all allowed petitions in Arbitration and Alternate Dispute Resolution Category
See all Dismissed petitions in Arbitration and Alternate Dispute Resolution Category
See all partially allowed petitions in Arbitration and Alternate Dispute Resolution Category

Similar Posts