Supreme Court Restores Enhanced Compensation for Landowners in Vadodara Canal Project image for SC Judgment dated 16-08-2023 in the case of Kalubhai Khatubhai & Others vs State of Gujarat & Others
| |

Supreme Court Restores Enhanced Compensation for Landowners in Vadodara Canal Project

The case of Kalubhai Khatubhai & Others vs. State of Gujarat & Others is a landmark judgment concerning land acquisition compensation. The Supreme Court reinstated the compensation awarded by the Reference Court after it was reduced by the Gujarat High Court. This case highlights the principles of fair compensation, equality in land acquisition cases, and the significance of government consistency in disbursing compensation.

Background of the Case

The landowners involved in the case were affected by the Vadodara Branch Canal of the Narmada Project. The State of Gujarat had acquired lands from villages Morlipura, Kumetha, and Nimeta under the Land Acquisition Act, 1894. The process started with notifications issued under Section 4 of the Act on different dates, and the Reference Court enhanced the compensation for the acquired land. However, the Gujarat High Court later reduced the compensation, leading to the appeal before the Supreme Court.

Read also: https://judgmentlibrary.com/supreme-court-rejects-adverse-possession-claim-over-government-land-in-kerala/

Chronology of Events

  • The lands in question were acquired in multiple phases through notifications issued under Section 4 of the Land Acquisition Act.
  • The Land Acquisition Officer (LAO) initially awarded compensation at Rs. 19,000 per hectare.
  • The landowners sought reference under Section 18 of the Act, leading to a decision by the Reference Court, which enhanced the compensation to Rs. 4,00,000 per hectare.
  • The Gujarat High Court, upon appeal by the State, reduced the compensation by half, restoring the original LAO award.
  • Aggrieved landowners approached the Supreme Court.

Arguments by the Appellants (Landowners)

The appellants contested the High Court’s decision, presenting the following arguments:

  • The Reference Court had rightfully determined the market value based on comparable cases and principles of fair compensation.
  • The High Court wrongly relied on an earlier case involving land acquisition in village Nimeta, which had different acquisition dates and land value considerations.
  • Landowners from the same village had been awarded Rs. 4,00,000 per hectare in a later case, and the government accepted that decision without appeal.
  • Differential treatment among similarly placed landowners violated the principle of equality.

Arguments by the Respondents (State of Gujarat)

The State defended the High Court’s ruling, arguing:

  • The compensation originally awarded by the LAO was justified.
  • The High Court’s reliance on earlier decisions was in line with legal precedent.
  • Excessive compensation could create a financial burden on the state.

Key Observations by the Supreme Court

The Supreme Court analyzed the facts and made the following key observations:

“The High Court was right in its interference with the order of the Reference Court while holding that acquisition of lands in village Dumad (which were not acquired for the project) could not be a guiding factor for determining compensation. However, at the same time, the learned Judge of the High Court fell in error in reducing the compensation payable to the appellants based on compensation awarded in respect of lands comprised in village Nimeta.”

Read also: https://judgmentlibrary.com/supreme-court-rules-on-assigned-land-resumption-in-telangana-legal-implications-and-analysis/

The Supreme Court held that the compensation reduction by the High Court was flawed because the land acquisition for village Nimeta happened five years earlier. Therefore, using that case as a benchmark was inappropriate.

Equal Treatment Among Landowners

The Supreme Court further noted:

“The appellants cannot be worse off than the other affected landowners of the same village, i.e., Morlipura, who have been paid more compensation. In a welfare state like ours where we have promised all the citizens social and economic justice, it would be fair and just if the appellants are meted equal treatment as the other affected landowners.”

Read also: https://judgmentlibrary.com/supreme-court-restores-property-sale-validity-of-sale-deed-and-unilateral-cancellation-discussed/

The Court highlighted the importance of uniformity and fairness in compensation for land acquisition cases.

Final Judgment

In light of its observations, the Supreme Court:

  • Set aside the Gujarat High Court’s ruling.
  • Restored the Reference Court’s award of Rs. 4,00,000 per hectare.
  • Directed the government to pay the outstanding compensation with 5% simple interest from May 10, 2007.

The Supreme Court’s decision upholds the fundamental right to fair compensation and reinforces the principle of equal treatment for similarly placed landowners.


Petitioner Name: Kalubhai Khatubhai & Others.
Respondent Name: State of Gujarat & Others.
Judgment By: Justice Bela M. Trivedi, Justice Dipankar Datta.
Place Of Incident: Vadodara, Gujarat.
Judgment Date: 16-08-2023.

Don’t miss out on the full details! Download the complete judgment in PDF format below and gain valuable insights instantly!

Download Judgment: kalubhai-khatubhai-&-vs-state-of-gujarat-&-o-supreme-court-of-india-judgment-dated-16-08-2023.pdf

Directly Download Judgment: Directly download this Judgment

See all petitions in Property Disputes
See all petitions in Damages and Compensation
See all petitions in Judgment by Bela M. Trivedi
See all petitions in Judgment by Dipankar Datta
See all petitions in allowed
See all petitions in supreme court of India judgments August 2023
See all petitions in 2023 judgments

See all posts in Civil Cases Category
See all allowed petitions in Civil Cases Category
See all Dismissed petitions in Civil Cases Category
See all partially allowed petitions in Civil Cases Category

Similar Posts