Supreme Court Rejects Plea for Fresh Arbitration in India Power Corporation vs. Eastern Coalfields Dispute image for SC Judgment dated 15-03-2022 in the case of India Power Corporation Ltd. vs Eastern Coalfields Limited
| |

Supreme Court Rejects Plea for Fresh Arbitration in India Power Corporation vs. Eastern Coalfields Dispute

The case of India Power Corporation Ltd. vs. Eastern Coalfields Limited is a significant ruling on arbitration proceedings and the finality of arbitral awards. The Supreme Court’s judgment clarifies the scope of challenging arbitration awards and reaffirms that arbitration awards, once made, cannot be reopened unless specific legal grounds under the Arbitration and Conciliation Act, 1996 are met.

The appeal was filed by Eastern Coalfields Limited (ECL) seeking the appointment of a fresh arbitrator to examine a specific report that was not adjudicated upon in the original arbitration. The Supreme Court, after analyzing the facts and legal precedents, rejected the plea, holding that the original award was final and that the matter could not be reopened.

Background of the Case

The dispute originated from a contractual agreement between India Power Corporation Ltd. (IPCL) and Eastern Coalfields Limited (ECL). The dispute was referred to arbitration, and the Supreme Court had previously appointed Justice S.S. Nijjar (Retd.) as the sole arbitrator in 2014.

Read also: https://judgmentlibrary.com/arbitration-clause-and-non-arbitrability-supreme-court-clarifies-scope-of-section-11-petitions/

The arbitrator rendered his award on February 15, 2021, granting compensation to both parties:

  • IPCL was awarded Rs. 24.72 crores with 9% interest from October 6, 2016, until payment.
  • ECL was awarded Rs. 18.66 crores with 9% interest from October 6, 2016, until payment.

Following the award, ECL approached the Supreme Court, arguing that a specific issue related to the MECON report had not been adjudicated upon and sought the appointment of a fresh arbitrator.

Arguments Presented by the Petitioner

The petitioner, Eastern Coalfields Limited (ECL), contended:

  • The arbitrator could not adjudicate upon the MECON report, as it required further evidence.
  • Since the arbitrator passed away soon after delivering the award, a new arbitrator should be appointed to address the issue.
  • The matter related to the computation of rent payable to ECL for the period between March 2016 and October 2016, which was allegedly left out of the final award.
  • The application was maintainable under Section 33 of the Arbitration and Conciliation Act, 1996, which allows corrections and interpretations of arbitral awards.

Arguments Presented by the Respondent

India Power Corporation Ltd. (IPCL) opposed the petition, arguing:

  • The award was final and had already settled the claims and counterclaims.
  • The MECON report issue was part of an amendment request to ECL’s counterclaim, which was dismissed during the arbitration proceedings.
  • ECL had the option of filing objections under Section 34 of the Arbitration Act, but instead, they sought to reopen the arbitration under the guise of appointing a new arbitrator.
  • The Delhi High Court had already rejected similar objections raised by ECL under Section 34, and the present application was an attempt to circumvent that ruling.

Supreme Court’s Observations and Verdict

The Supreme Court analyzed the legal basis for reopening an arbitral award and made the following key observations:

  • The MECON report issue was already considered in the arbitration process, and the arbitrator had dismissed ECL’s amendment request regarding it.
  • Paragraphs 157 to 161 of the arbitration award indicated that the arbitrator had thoroughly examined the dispute and had not left any part unresolved.
  • The prayer for appointing a new arbitrator was an attempt to reopen an already concluded arbitration, which was impermissible.
  • The Delhi High Court had already rejected ECL’s objections under Section 34, confirming that the award was final.
  • Section 33 of the Arbitration Act could not be used to re-adjudicate issues that were already considered.

In light of these findings, the Supreme Court ruled:

  • The application for appointing a new arbitrator was dismissed.
  • The arbitration award dated February 15, 2021, was upheld as final and binding.
  • ECL was barred from making any further claims related to the MECON report.

Legal Precedents Considered

The Supreme Court referred to multiple cases on arbitration and the finality of arbitral awards:

  • McDermott International Inc. v. Burn Standard Co. Ltd. (2006): Held that courts cannot interfere with arbitral awards except under limited grounds prescribed in the Arbitration Act.
  • Hindustan Zinc Ltd. v. Friends Coal Carbonisation (2006): Reiterated that arbitration awards are binding unless successfully challenged under Section 34.
  • Associated Builders v. Delhi Development Authority (2015): Established that an arbitral award can only be set aside on limited grounds such as patent illegality or perversity.

Impact of the Judgment

This ruling has significant implications for arbitration proceedings in India:

  • It reinforces the principle that arbitral awards are final and binding and cannot be reopened through indirect means.
  • It limits the scope of challenging arbitration awards under Section 33 and prevents parties from attempting to introduce new claims post-award.
  • It provides clarity on the scope of judicial intervention in arbitration matters, ensuring minimal court interference.
  • The decision strengthens India’s arbitration framework by ensuring that once disputes are settled, they remain settled.

By rejecting ECL’s plea, the Supreme Court has upheld the sanctity of arbitration proceedings and ensured that arbitral awards retain their finality.


Petitioner Name: India Power Corporation Ltd..
Respondent Name: Eastern Coalfields Limited.
Judgment By: Justice Vikram Nath, Justice M.M. Sundresh.
Place Of Incident: India.
Judgment Date: 15-03-2022.

Don’t miss out on the full details! Download the complete judgment in PDF format below and gain valuable insights instantly!

Download Judgment: india-power-corporat-vs-eastern-coalfields-l-supreme-court-of-india-judgment-dated-15-03-2022.pdf

Directly Download Judgment: Directly download this Judgment

See all petitions in Arbitration Awards
See all petitions in Enforcement of Awards
See all petitions in Judgment by Vikram Nath
See all petitions in Judgment by M.M. Sundresh
See all petitions in dismissed
See all petitions in Quashed
See all petitions in supreme court of India judgments March 2022
See all petitions in 2022 judgments

See all posts in Arbitration and Alternate Dispute Resolution Category
See all allowed petitions in Arbitration and Alternate Dispute Resolution Category
See all Dismissed petitions in Arbitration and Alternate Dispute Resolution Category
See all partially allowed petitions in Arbitration and Alternate Dispute Resolution Category

Similar Posts