Supreme Court Orders Refund to Tomorrowland Limited in HUDCO Land Dispute image for SC Judgment dated 13-02-2025 in the case of M/s. Tomorrowland Limited vs Housing and Urban Development
| |

Supreme Court Orders Refund to Tomorrowland Limited in HUDCO Land Dispute

The Supreme Court of India, in its judgment dated February 13, 2025, ruled in favor of M/s. Tomorrowland Limited, ordering the Housing and Urban Development Corporation Limited (HUDCO) to refund Rs. 28.11 crores, which was forfeited due to alleged non-performance of contractual obligations. However, the Court denied the appellant’s claim for interest on the refunded amount, citing the appellant’s conduct, including forum shopping and procedural delays.

Background of the Case

The dispute revolves around a 99-year lease agreement for a five-star hotel project in Andrew’s Ganj, New Delhi, initiated by the Ministry of Urban Development in 1990. HUDCO, acting as the executing agency, allotted the project to Tomorrowland Limited (formerly M S Shoes East Ltd.) as the highest bidder. The allotment letter, issued on October 31, 1994, stipulated payment terms amounting to Rs. 64.10 crores for the hotel site and Rs. 14 crores for the car parking space.

Read also: https://judgmentlibrary.com/supreme-court-rules-on-sebi-regulations-open-offer-and-competing-bids-in-corporate-takeover/

Tomorrowland Limited paid Rs. 28.11 crores as the first installment but later objected to further payments, arguing that HUDCO had failed to fulfill its contractual obligations, including obtaining statutory approvals under the Urban Land (Ceiling and Regulation) Act, 1976, and the Income Tax Act, 1961. Consequently, HUDCO canceled the allotment on May 2, 1996, and forfeited the deposited amount.

Petitioner’s Claims (Tomorrowland Limited)

Tomorrowland Limited argued:

  • HUDCO misrepresented its ability to execute a sub-lease, as it lacked a perpetual lease from the government at the time of allotment.
  • The forfeiture of Rs. 28.11 crores was unlawful since the company had made payments in good faith.
  • The company was treated unfairly compared to another bidder, Ansal Properties & Industries Limited, which was granted interest-free extensions on its payments.
  • The forfeited amount should be refunded along with interest at the contractual rate of 16.48% per annum.

Respondent’s Defense (HUDCO)

HUDCO countered these claims, asserting:

  • Tomorrowland Limited defaulted on the payment schedule, leading to a legitimate cancellation of the allotment.
  • The company engaged in forum shopping, withdrawing an initial suit in the High Court and refiling in a lower civil court to circumvent jurisdiction.
  • The forfeiture clause in the allotment letter was valid, and Tomorrowland had failed to meet its obligations.
  • The company did not pay the required court fees for possession claims, weakening its case.

Supreme Court’s Observations

The Supreme Court examined the contractual obligations and found that HUDCO had indeed failed to fulfill its reciprocal obligations, particularly:

  • HUDCO did not obtain statutory approvals necessary for executing the sub-lease.
  • HUDCO lacked the perpetual lease to transfer possession of the hotel site.
  • HUDCO’s failure to secure the revised layout plan approval for the project led to disputes even with subsequent bidders.

Regarding the appellant’s conduct, the Court noted:

“The material on record sufficiently indicates that the Appellant did not approach the Court with clean hands and instead attempted to hoodwink the judicial process by creating a facade to subterfuge their inability to meet their contractual obligations.”

Read also: https://judgmentlibrary.com/supreme-court-upholds-private-bus-operators-rights-in-karnataka-landmark-ruling-on-transport-permits/

Despite ruling in favor of Tomorrowland Limited on the issue of refund, the Court denied interest on the amount, emphasizing that the company’s actions undermined its claim for equitable relief.

Final Judgment

The Supreme Court ruled:

  • HUDCO must refund Rs. 28.11 crores to Tomorrowland Limited within three months.
  • No interest would be payable on the refunded amount due to the appellant’s conduct.
  • If HUDCO fails to refund the amount within the stipulated period, interest at 6% per annum will be applied until the amount is realized.
  • The decision is limited to the five-star hotel project and does not affect other pending disputes related to the Andrew’s Ganj development.

Impact of the Judgment

This judgment clarifies key principles of contract law and public bidding:

  • Enforcement of Reciprocal Obligations: Developers must ensure that executing agencies fulfill their obligations before demanding payments.
  • Judicial View on Forfeiture Clauses: The Court reaffirmed that forfeiture cannot be enforced when the forfeiting party is in breach of contract.
  • Clean Hands Doctrine: Equitable relief, such as interest on refunds, can be denied if a litigant engages in forum shopping or other procedural tactics.

Conclusion

The Supreme Court’s decision in Tomorrowland Limited vs. HUDCO sets a precedent for balancing contractual fairness with judicial integrity. While the company secured a refund, its strategic litigation tactics cost it significant financial compensation. This ruling reinforces the principle that legal disputes must be approached with transparency and good faith to receive full relief.

Read also: https://judgmentlibrary.com/supreme-court-rules-on-mortgage-priority-in-banking-dispute-between-cosmos-bank-and-central-bank-of-india/


Petitioner Name: M/s. Tomorrowland Limited.
Respondent Name: Housing and Urban Development Corporation Limited & Another.
Judgment By: Justice Surya Kant, Justice Ujjal Bhuyan.
Place Of Incident: New Delhi.
Judgment Date: 13-02-2025.

Don’t miss out on the full details! Download the complete judgment in PDF format below and gain valuable insights instantly!

Download Judgment: ms.-tomorrowland-li-vs-housing-and-urban-de-supreme-court-of-india-judgment-dated-13-02-2025.pdf

Directly Download Judgment: Directly download this Judgment

See all petitions in Contract Disputes
See all petitions in Corporate Compliance
See all petitions in unfair trade practices
See all petitions in Judgment by Surya Kant
See all petitions in Judgment by Ujjal Bhuyan
See all petitions in partially allowed
See all petitions in Modified
See all petitions in supreme court of India judgments February 2025
See all petitions in 2025 judgments

See all posts in Corporate and Commercial Cases Category
See all allowed petitions in Corporate and Commercial Cases Category
See all Dismissed petitions in Corporate and Commercial Cases Category
See all partially allowed petitions in Corporate and Commercial Cases Category

Similar Posts