Land Acquisition Compensation: Supreme Court Rules on Developer's Locus Standi image for SC Judgment dated 05-10-2021 in the case of Shrachi Burdwan Developers Pri vs The State of West Bengal & Ors
| |

Land Acquisition Compensation: Supreme Court Rules on Developer’s Locus Standi

The Supreme Court of India, in the case of Shrachi Burdwan Developers Private Limited v. The State of West Bengal & Ors., examined the issue of land acquisition compensation and the locus standi of developers in challenging compensation awards. The case, Civil Appeal No. 5856 of 2021, arose from disputes regarding the compensation awarded to landowners whose land was acquired for a satellite township project in Burdwan, West Bengal. The Supreme Court, in its judgment dated October 5, 2021, delivered by M.R. Shah and A.S. Bopanna, ruled on the maintainability of the developer’s petition challenging the compensation award and the jurisdiction of the High Court under Article 226.

Background of the Case

The case revolves around land acquisition undertaken by the Burdwan Development Authority (BDA) for the development of a satellite township. The Government of West Bengal issued notifications under Section 4 of the Land Acquisition Act, 1894, in April and May 2005, stating that the land was acquired for a public purpose. The declaration under Section 6 was subsequently issued, and the landowners were compensated based on the awards declared by the Land Acquisition Collector.

In response to the acquisition, a group of landowners filed a writ petition before the Calcutta High Court, claiming that the acquisition was not for a public purpose but for the benefit of Bengal Shrachi Housing Development Ltd., a private entity. However, the High Court upheld the acquisition, stating that it was for a public purpose and at public expense.

Read also: https://judgmentlibrary.com/electricity-billing-dispute-supreme-court-upholds-short-assessment-recovery-in-prem-cottex-v-uttar-haryana-bijli-vitran-nigam-ltd/

Despite this, the landowners sought a higher compensation amount, and the Reference Court enhanced the compensation from Rs. 5,80,700 per acre to Rs. 35,00,000 per acre. The enhancement led to further disputes, particularly regarding who was liable to pay the increased compensation.

Key Issues Before the Court

  • Whether Shrachi Burdwan Developers Pvt. Ltd. had the locus standi to challenge the compensation award?
  • Whether the High Court was justified in entertaining the developer’s writ petition under Article 226 of the Constitution?
  • Whether the compensation enhancement by the Reference Court was valid?

Petitioner’s Arguments

The appellant, Shrachi Burdwan Developers Pvt. Ltd., contended that:

  • As a developer of the project under a public-private partnership (PPP) agreement, it had a direct interest in the compensation proceedings.
  • The enhanced compensation significantly increased the project cost, affecting its financial viability.
  • Since the Reference Court passed the award without impleading it as a party, the order violated the principles of natural justice.
  • The High Court, under Article 226, had jurisdiction to entertain its writ petition challenging the enhanced compensation.
  • The Single Judge of the Calcutta High Court had rightly quashed the compensation award, but the Division Bench erred in overturning it.

Respondent’s Arguments

The landowners and the State of West Bengal countered that:

  • The developer was not a person interested under Section 3(b) of the Land Acquisition Act and thus had no right to challenge the award.
  • The compensation amount was determined through proper judicial process, and the developer had no direct legal standing to dispute it.
  • The High Court’s Division Bench was correct in ruling that a developer cannot challenge a compensation award meant for landowners.
  • The public-private partnership agreement between the BDA and the developer did not confer any direct right over land compensation proceedings.

Supreme Court’s Judgment

The Supreme Court ruled against the developer and upheld the compensation enhancement awarded by the Reference Court. The key findings were:

  • The developer was not a person interested under Section 3(b) of the Land Acquisition Act since the land was acquired for a public purpose.
  • The obligation to pay compensation remained with the Burdwan Development Authority, and the developer’s financial concerns were not relevant to the compensation dispute.
  • The High Court’s Single Judge had exceeded jurisdiction by quashing the compensation award under Article 226.
  • Compensation awards must be challenged under Section 54 of the Land Acquisition Act and not through writ petitions.

Key Extract from the Judgment

“The appellant is not a ‘person interested’ within the meaning of Section 3(b) of the Act and has no locus to challenge the enhancement of compensation. The Division Bench of the High Court rightly set aside the order of the Single Judge.”

Final Verdict

  • The Supreme Court dismissed the appeal of Shrachi Burdwan Developers Pvt. Ltd.
  • The Division Bench’s order, upholding the compensation award, was affirmed.
  • The developer was advised to pursue other remedies, including filing an appeal under Section 54 of the Land Acquisition Act if it could establish locus standi.

Impact of the Judgment

This ruling has far-reaching implications for land acquisition disputes involving public-private partnerships and real estate developers. The decision:

  • Clarifies that only landowners and acquiring authorities can contest compensation awards.
  • Limits the ability of private developers to interfere in compensation disputes.
  • Reaffirms that writ jurisdiction cannot be used to bypass statutory appeal mechanisms.
  • Ensures that compensation disputes are resolved through statutory channels rather than judicial shortcuts.

This landmark case establishes a clear precedent for similar disputes involving land acquisition and developer rights.


Petitioner Name: Shrachi Burdwan Developers Private Limited.
Respondent Name: The State of West Bengal & Ors..
Judgment By: Justice M.R. Shah, Justice A.S. Bopanna.
Place Of Incident: Burdwan, West Bengal.
Judgment Date: 05-10-2021.

Don’t miss out on the full details! Download the complete judgment in PDF format below and gain valuable insights instantly!

Download Judgment: shrachi-burdwan-deve-vs-the-state-of-west-be-supreme-court-of-india-judgment-dated-05-10-2021.pdf

Directly Download Judgment: Directly download this Judgment

See all petitions in Property Disputes
See all petitions in Damages and Compensation
See all petitions in Landlord-Tenant Disputes
See all petitions in Judgment by Mukeshkumar Rasikbhai Shah
See all petitions in Judgment by A. S. Bopanna
See all petitions in dismissed
See all petitions in Quashed
See all petitions in supreme court of India judgments October 2021
See all petitions in 2021 judgments

See all posts in Civil Cases Category
See all allowed petitions in Civil Cases Category
See all Dismissed petitions in Civil Cases Category
See all partially allowed petitions in Civil Cases Category

Similar Posts